Cabinet Manufacturing 실적

CABINET MANUFACTURING 실적

2023

01. 삼성전자 P3 & P4 PJT

– Fire Alarm Control Panel 65EA Fabrication

 

2022

11월 SHWE P3 PJT

– DCS Control Panel 18EA Fabrication

07월 HTC ACP PJT

– Fire Alarm Control Panel 5EA Fabrication

 

07월 삼성전자 P3 & P4 PJT

– Fire Alarm Control Panel 40EA Fabrication

05월 OUMACHE III 1300MW CCPP PJT

– Baker Hughes Vibration Monitoring System Panel 6EA Engineering & Fabrication

 

05월 Petrobras PJT

– Baker Hughes Vibration Monitoring System Panel 1EA Fabrication

 

03월 SK DAKAR PJT

– Vibration Monitoring System Panel 153EA Fabrication

 

02월 DOS BOCAS Refineray PJT

– Fire Alarm Control Panel 27EA Fabrication

 

02월 SARAWAK Methanol PJT

– Vibration Monitoring System Panel 8EA Fabrication

2021

09월 삼성전자 P3 PJT

– HONEYWELL Fire Alarm Control Panel 60EA Fabrication

09 Machine Monitoring System (TOYO) PJT

– Baker Hughes Vibration Monitoring System Panel 5EA Engineering & Fabrication

06 이천 스마트에너지센터 건설 VMS PJT

– Baker Hughes Vibration Monitoring System Panel 4EA Engineering & Fabrication

04 EDISON-IV (SBL P4 BMS) PJT

– EMERSON DCS Control Panel 156EA Fabrication

04 HTC 방재센터 시스템 이설공서 PJT

– HONEYWELL Fire Alarm Control Panel 55EA Fabrication

04 GYHP PJT

– EMERSON DCS Control Panel 10EA Engineering & Fabrication

02 GTG MarkV to MarkVIe Upgrade PJT

– Baker Hughes Nexus Controls Panel 2EA Engineering & Fabrication

01 여주 CCPP Vibration Monitoring System PJT

– Baker Hughes Vibration Monitoring System Panel 2EA Engineering & Fabrication

 

2020

12월 인도네시아 RDMP Balikpapan PJT

– Baker Hughes Vibration Monitoring System Panel 49EA Engineering & Fabrication

10월 태국 HMC PP4 PJT

– HONEYWELL Fire Alarm Control Panel 4EA Fabrication

09월 베트남 LSP Package PJT

– Baker Hughes MMS System Panel 4EA Engineering & Fabrication

08월 KCC DCS Upgrade PJT

– EMERSON DCS Control Panel 12EA Fabrication

08월 폴란드 PDHPP PJT

– Baker Hughes MMS System Panel 29EA Engineering & Fabrication

06월 LNG CANADA JGC (JGC/SIEMENS/WASCO) PJT

– HONEYWELL Fire Alarm Control Panel 31EA Fabrication

06월 LNG CANADA PJT

– GE MMS System Panel 27EA Engineering & Fabrication

03월 안양열병합발전소 2-2호기 건설공사 PJT

– GE MMS System Panel 3EA Engineering & Fabrication

03월 대산 HTC PP4 PJT

– HONEYWELL Fire Alarm Control Panel 7EA Fabrication

02월 아랍에미레이트 ADNOC Refining Waste Heat Recovery (Takreer) PJT

– GE MMS System Panel 12EA Engineering & Fabrication

02월 TORAY Revamping PJT

– EMERSON DCS Control Panel 20EA Engineering & Fabrication

02월 GBARAN UBIE Phase III Infill (GBU III) PJT

– EMERSON DCS Control Panel 8EA Fabrication

2019

07월 남제주 Combined Cycle Power Plant PJT

– GE MMS System Panel 5EA Engineering & Fabrication

04월 대산 ADL PJT

– HONEYWELL Fire Alarm Control Panel 4EA Fabrication & Site Installation

04월 태국 PTT ORG PJT

– GE MMS System Panel 10EA Engineering & Fabrication

04월 태국 POSCO MMS BANKCHAK BCP PJT

– GE MMS System Panel 11EA Engineering & Fabrication

02월 태국 Propylene Oxide PJT

– HONEYWELL Fire Alarm Control Panel 10EA Fabrication

 

2018

08월 우주베키스탄 UGTL PJT

– GE MMS System Panel 26EA Engineering & Fabrication

– HONEYWELL Fire Alarm Control Panel 22EA & Module Box 330EA Fabrication

08월 Mad Dog 2 PJT

– GE MMS System Panel 12EA Engineering & Fabrication

06월 이라크 KARBALA Refinery (3rd) PJT

– GE MMS System Panel 12EA Engineering & Fabrication

06월 이라크 KARBALA Refinery (2nd) PJT

– GE MMS System Panel 14EA Engineering & Fabrication

05월 쿠웨이트 AL-ZOUR LNG Import PJT

– HONEYWELL Fire Alarm Control Panel 16EA Fabrication

01월 청주 SK Hynix M15 Ph1 PJT

– EMERSON DCS Control Panel 6EA Engineering, Fabrication & Site Installation

 

2017

12월 오만 LPIC PJT

– GE MMS System Panel 9EA Engineering & Fabrication

09월 오만 LIWA PJT

– GE MMS System Panel 2EA Engineering & Fabrication 09 바레인 BAHRAIN LNG Import Terminal PJT

– EMERSON MHM System Panel 5EA Fabrication

09월 사우디아라비아 IMC Efficiency Enhancement PJT

– EMERSON DCS Control Panel 6EA Engineering & Fabrication

– GE MMS System Panel 2EA Engineering & Fabrication

07월 오산 S-OIL PJT

– GE MMS System Panel 7EA Engineering & Fabrication

07월 안양 열병합발전소 2호기 건설공사 PJT

– GE MMS System Panel 3EA Engineering & Fabrication

05월 파나마 PANAMA COLON Gas PJT

– EMERSON DCS Control Panel 26EA Fabrication & Site Installation

02월 삼천포 2nd Therminal Power Plant PJT

– EMERSON MHM System Panel 5EA Fabrication

 

2016

12월 여수 BASF Ultrason PJT

– EMERSON DCS System Panel 10EA Fabrication

09월 LG Chemical SSBR PJT

– EMERSON DCS System Panel 3EA Fabrication

08월 삼천포 1st Therminal Power Plant PJT

– EMERSON MHM System Panel 5EA Fabrication

07월 인천 EDISON-III PJT

– EMERSON DCS Control Panel 87EA Engineering & Fabrication

05월 평택 HANMI Bioplant-2 PJT

– EMERSON DCS Control Panel 13EA Engineering & Fabrication

04월 태국 POSCO MMS BANGCHAK BCP PJT

– GE MMS System Panel 2EA Engineering & Fabrication

04월 아랍에미레이트 NEB-3 PJT

– EMERSON DCS Control Panel 8EA Fabrication

 

2015

12월 이라크 KARBALA Refinery PJT

– GE MMS System Panel 16EA Engineering & Fabrication

– AB PLC for Raw Water Package Control Panel 11EA Fabrication

11월 KUKDO SK PJT

– EMERSON DCS Control Panel 12EA Fabrication & Site Installation

09월 NDBR LG PJT

– EMERSON DCS Control Panel 2EA Fabrication & Site Installation

07월 말레이시아 DIC_Fast Track PJT

– GE MMS System Panel 5EA Engineering & Fabrication

07월 카자흐스탄 POCR Refinery PJT

– EMERSON DCS Control Panel 2EA Fabrication

04월 나이지리아 GBU Infill Ph2 PJT

– EMERSON DCS Control Panel 20EA Fabrication

03월 쿠웨이트 KNPC CFP PJT

– EMERSON DCS Control Panel 20EA Fabrication

 

2014

12월 울산 SK Gas PDH PJT

– EMERSON DCS & SIS Control Panel 51EA Fabrication & Site Installation

11월 태국 IRPC UHV PJT

– EMERSON DCS Control Panel 4EA Fabrication

06월 대산 HDO PJT

– EMERSON DCS Control Panel 53EA Fabrication & Site Installation

05월 EDISON-II Utility Management System PJT

– EMERSON DCS Control Panel 15EA Fabrication & Site Installation

01월 태국 IRPC UHV PJT

– GE MMS System Panel 18EA Engineering & Fabrication

 

2013

12월 사우디아라비아 Butanol PJT

– GE MMS System Panel 3EA Fabrication

07월 쿠웨이트 ES PJT

– EMERSON DCS Control Panel 32EA Fabrication

05월 ACS PJT

– EMERSON DCS Control Panel 21EA Fabrication

03월 쿠웨이트 WARA EIP PJT

– EMERSON DCS Control Panel 40EA Fabrication & Site Installation

02월 쿠웨이트 WARA WPMP PJT

– EMERSON DCS Control Panel 35EA Fabrication

 

2012

01월 TORAY KL7 & KL11 PJT

– EMERSON DCS Control Panel 60EA Fabrication & Site Installation

 

2011

10월 Float Glass Line #6 PJT

– EMERSON DCS Control Panel 18EA Fabrication & Site Installation

10월 JPP PJT

– EMERSON DCS Control Panel 116EA Fabrication & Site Installation

07월 T-GAS PJT

– EMERSON DCS Control Panel 120EA Fabrication & Site Installation

 

2010

10월 캐나다 Kearl Oil Sands PJT

– EMERSON DCS Control Panel 81EA Fabrication 

 