Cabinet Manufacturing 실적
CABINET MANUFACTURING 실적
2023
01. 삼성전자 P3 & P4 PJT
– Fire Alarm Control Panel 65EA Fabrication
2022
11월 SHWE P3 PJT
– DCS Control Panel 18EA Fabrication
07월 HTC ACP PJT
– Fire Alarm Control Panel 5EA Fabrication
07월 삼성전자 P3 & P4 PJT
– Fire Alarm Control Panel 40EA Fabrication
05월 OUMACHE III 1300MW CCPP PJT
– Baker Hughes Vibration Monitoring System Panel 6EA Engineering & Fabrication
05월 Petrobras PJT
– Baker Hughes Vibration Monitoring System Panel 1EA Fabrication
03월 SK DAKAR PJT
– Vibration Monitoring System Panel 153EA Fabrication
02월 DOS BOCAS Refineray PJT
– Fire Alarm Control Panel 27EA Fabrication
02월 SARAWAK Methanol PJT
– Vibration Monitoring System Panel 8EA Fabrication
2021
09월 삼성전자 P3 PJT
– HONEYWELL Fire Alarm Control Panel 60EA Fabrication
09 Machine Monitoring System (TOYO) PJT
– Baker Hughes Vibration Monitoring System Panel 5EA Engineering & Fabrication
06 이천 스마트에너지센터 건설 VMS PJT
– Baker Hughes Vibration Monitoring System Panel 4EA Engineering & Fabrication
04 EDISON-IV (SBL P4 BMS) PJT
– EMERSON DCS Control Panel 156EA Fabrication
04 HTC 방재센터 시스템 이설공서 PJT
– HONEYWELL Fire Alarm Control Panel 55EA Fabrication
04 GYHP PJT
– EMERSON DCS Control Panel 10EA Engineering & Fabrication
02 GTG MarkV to MarkVIe Upgrade PJT
– Baker Hughes Nexus Controls Panel 2EA Engineering & Fabrication
01 여주 CCPP Vibration Monitoring System PJT
– Baker Hughes Vibration Monitoring System Panel 2EA Engineering & Fabrication
2020
12월 인도네시아 RDMP Balikpapan PJT
– Baker Hughes Vibration Monitoring System Panel 49EA Engineering & Fabrication
10월 태국 HMC PP4 PJT
– HONEYWELL Fire Alarm Control Panel 4EA Fabrication
09월 베트남 LSP Package PJT
– Baker Hughes MMS System Panel 4EA Engineering & Fabrication
08월 KCC DCS Upgrade PJT
– EMERSON DCS Control Panel 12EA Fabrication
08월 폴란드 PDHPP PJT
– Baker Hughes MMS System Panel 29EA Engineering & Fabrication
06월 LNG CANADA JGC (JGC/SIEMENS/WASCO) PJT
– HONEYWELL Fire Alarm Control Panel 31EA Fabrication
06월 LNG CANADA PJT
– GE MMS System Panel 27EA Engineering & Fabrication
03월 안양열병합발전소 2-2호기 건설공사 PJT
– GE MMS System Panel 3EA Engineering & Fabrication
03월 대산 HTC PP4 PJT
– HONEYWELL Fire Alarm Control Panel 7EA Fabrication
02월 아랍에미레이트 ADNOC Refining Waste Heat Recovery (Takreer) PJT
– GE MMS System Panel 12EA Engineering & Fabrication
02월 TORAY Revamping PJT
– EMERSON DCS Control Panel 20EA Engineering & Fabrication
02월 GBARAN UBIE Phase III Infill (GBU III) PJT
– EMERSON DCS Control Panel 8EA Fabrication
2019
07월 남제주 Combined Cycle Power Plant PJT
– GE MMS System Panel 5EA Engineering & Fabrication
04월 대산 ADL PJT
– HONEYWELL Fire Alarm Control Panel 4EA Fabrication & Site Installation
04월 태국 PTT ORG PJT
– GE MMS System Panel 10EA Engineering & Fabrication
04월 태국 POSCO MMS BANKCHAK BCP PJT
– GE MMS System Panel 11EA Engineering & Fabrication
02월 태국 Propylene Oxide PJT
– HONEYWELL Fire Alarm Control Panel 10EA Fabrication
2018
08월 우주베키스탄 UGTL PJT
– GE MMS System Panel 26EA Engineering & Fabrication
– HONEYWELL Fire Alarm Control Panel 22EA & Module Box 330EA Fabrication
08월 Mad Dog 2 PJT
– GE MMS System Panel 12EA Engineering & Fabrication
06월 이라크 KARBALA Refinery (3rd) PJT
– GE MMS System Panel 12EA Engineering & Fabrication
06월 이라크 KARBALA Refinery (2nd) PJT
– GE MMS System Panel 14EA Engineering & Fabrication
05월 쿠웨이트 AL-ZOUR LNG Import PJT
– HONEYWELL Fire Alarm Control Panel 16EA Fabrication
01월 청주 SK Hynix M15 Ph1 PJT
– EMERSON DCS Control Panel 6EA Engineering, Fabrication & Site Installation
2017
12월 오만 LPIC PJT
– GE MMS System Panel 9EA Engineering & Fabrication
09월 오만 LIWA PJT
– GE MMS System Panel 2EA Engineering & Fabrication 09 바레인 BAHRAIN LNG Import Terminal PJT
– EMERSON MHM System Panel 5EA Fabrication
09월 사우디아라비아 IMC Efficiency Enhancement PJT
– EMERSON DCS Control Panel 6EA Engineering & Fabrication
– GE MMS System Panel 2EA Engineering & Fabrication
07월 오산 S-OIL PJT
– GE MMS System Panel 7EA Engineering & Fabrication
07월 안양 열병합발전소 2호기 건설공사 PJT
– GE MMS System Panel 3EA Engineering & Fabrication
05월 파나마 PANAMA COLON Gas PJT
– EMERSON DCS Control Panel 26EA Fabrication & Site Installation
02월 삼천포 2nd Therminal Power Plant PJT
– EMERSON MHM System Panel 5EA Fabrication
2016
12월 여수 BASF Ultrason PJT
– EMERSON DCS System Panel 10EA Fabrication
09월 LG Chemical SSBR PJT
– EMERSON DCS System Panel 3EA Fabrication
08월 삼천포 1st Therminal Power Plant PJT
– EMERSON MHM System Panel 5EA Fabrication
07월 인천 EDISON-III PJT
– EMERSON DCS Control Panel 87EA Engineering & Fabrication
05월 평택 HANMI Bioplant-2 PJT
– EMERSON DCS Control Panel 13EA Engineering & Fabrication
04월 태국 POSCO MMS BANGCHAK BCP PJT
– GE MMS System Panel 2EA Engineering & Fabrication
04월 아랍에미레이트 NEB-3 PJT
– EMERSON DCS Control Panel 8EA Fabrication
2015
12월 이라크 KARBALA Refinery PJT
– GE MMS System Panel 16EA Engineering & Fabrication
– AB PLC for Raw Water Package Control Panel 11EA Fabrication
11월 KUKDO SK PJT
– EMERSON DCS Control Panel 12EA Fabrication & Site Installation
09월 NDBR LG PJT
– EMERSON DCS Control Panel 2EA Fabrication & Site Installation
07월 말레이시아 DIC_Fast Track PJT
– GE MMS System Panel 5EA Engineering & Fabrication
07월 카자흐스탄 POCR Refinery PJT
– EMERSON DCS Control Panel 2EA Fabrication
04월 나이지리아 GBU Infill Ph2 PJT
– EMERSON DCS Control Panel 20EA Fabrication
03월 쿠웨이트 KNPC CFP PJT
– EMERSON DCS Control Panel 20EA Fabrication
2014
12월 울산 SK Gas PDH PJT
– EMERSON DCS & SIS Control Panel 51EA Fabrication & Site Installation
11월 태국 IRPC UHV PJT
– EMERSON DCS Control Panel 4EA Fabrication
06월 대산 HDO PJT
– EMERSON DCS Control Panel 53EA Fabrication & Site Installation
05월 EDISON-II Utility Management System PJT
– EMERSON DCS Control Panel 15EA Fabrication & Site Installation
01월 태국 IRPC UHV PJT
– GE MMS System Panel 18EA Engineering & Fabrication
2013
12월 사우디아라비아 Butanol PJT
– GE MMS System Panel 3EA Fabrication
07월 쿠웨이트 ES PJT
– EMERSON DCS Control Panel 32EA Fabrication
05월 ACS PJT
– EMERSON DCS Control Panel 21EA Fabrication
03월 쿠웨이트 WARA EIP PJT
– EMERSON DCS Control Panel 40EA Fabrication & Site Installation
02월 쿠웨이트 WARA WPMP PJT
– EMERSON DCS Control Panel 35EA Fabrication
2012
01월 TORAY KL7 & KL11 PJT
– EMERSON DCS Control Panel 60EA Fabrication & Site Installation
2011
10월 Float Glass Line #6 PJT
– EMERSON DCS Control Panel 18EA Fabrication & Site Installation
10월 JPP PJT
– EMERSON DCS Control Panel 116EA Fabrication & Site Installation
07월 T-GAS PJT
– EMERSON DCS Control Panel 120EA Fabrication & Site Installation
2010
10월 캐나다 Kearl Oil Sands PJT
– EMERSON DCS Control Panel 81EA Fabrication